Question: What inputs are necessary to build a schedule? Briefly summarize the steps involved in creating a schedule. What is the difference between task effort and
- What inputs are necessary to build a schedule?
- Briefly summarize the steps involved in creating a schedule.
- What is the difference between task effort and task duration?
- Why are milestones used in addition to task activities in a schedule?
- What is the purpose of a table or GANTT-style diagram of the schedule?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Inputs necessary to build a schedule include 1 Project Scope Statement Defines the project objectives deliverables and scope boundaries 2 Work Breakdo... View full answer