Question: What is a critical path? a The path that represents the shortest time in which a project could be finished. b None of the above

What is a critical path?
a
The path that represents the shortest time in which a project could be finished.
b
None of the above
c
The shortest path on a network diagram.
d
The longest path on a network diagram.