Question: What is an acceptable criterion for determining whether a project activity is on the critical path or not? The activity depends on the completion of

What is an acceptable criterion for determining

What is an acceptable criterion for determining whether a project activity is on the "critical path" or not? The activity depends on the completion of many other activities O b. A crash of this activity will result in a decrease of the total project cost A delay in completing the activity will result in a delay in completing the entire project d. The activity has many other activities that depend on it O e. None of the above