Question: What is an example of a damage a General Contractor might claim for delay on a project caused by the Owner? Group of answer choices
What is an example of a damage a General Contractor might claim for delay on a project caused by the Owner?
Group of answer choices
Extended field overhead.
Lost rents from tenants unable to occupy the building on time.
Lost profits from the building not being able to make goods for a period of time.
All of the above.