Question: What is 'float' or 'slack' in project scheduling?Question 7 Answera.Total project durationb.Time a task can be delayed without affecting the project end datec.Unassigned project resourcesd.Duration
What is 'float' or 'slack' in project scheduling?Question Answera.Total project durationb.Time a task can be delayed without affecting the project end datec.Unassigned project resourcesd.Duration of critical tasks