Question: What is not true regarding Work packages? Work Packages can be decomposed into smaller components called activities The Work Package is the work defined at
What is not true regarding Work packages?
Work Packages can be decomposed into smaller components called activities
The Work Package is the work defined at the lowest level of the WBS for which cost and duration can be estimated and managed
Each work package can be associated with more than one control account
The level of details for work packages will vary with the size and complexity of the Project