Question: What is the budgeted variable overhead cost rate per output unit? A. $36.00 B. $9.00 C. $10.00 D. $14.40 Really Great Corporation manufactures industrial-sized landscaping

What is the budgeted variable overhead cost rate per output unit? A. $36.00 B. $9.00 C. $10.00 D. $14.40
Really Great Corporation manufactures industrial-sized landscaping trailers and uses budgeted machine-hours to allocate variable manufacturing overhead The following information pertains to the company's manufactunng overhead data Budgeted output units Budgeted machine-hours Budgeted variable manufacturing overhead costs for 42,000 units Actual output units produced Actual machine-hours used Actual variable manufacturing overhead costs What is the budgeted variable overhead cost rate per output unit? 427000 units 10;500 hours S378;ooo 35250 units 14100 hours $352;500 O O 0 B. c. D. $3600 sgoo SID 00 $14 40