Question: What is the change in the objective function value if Drying Hours are increased to 1 5 0 and, simultaneously, Labor Hours are changed to

What is the change in the objective function value if Drying Hours are increased to 150 and, simultaneously, Labor Hours are changed to 200?
Variable Cells
Final
Reduced
Objective
Allowable
Allowable
Variable
Name
Value
Cost
Coefficient
Increase
Decrease
X
Product X
50
0
70
18
12
Y
Product Y
80
0
40
13
10
Constraints
Final
Shadow
Constraint
Allowable
Allowable
Number
Name
Value
Price
R.H. Side
Increase
Decrease
1
Drying Hours
100
5
100
110
50
2
Inspection Hours
1410
0
1800
200
70
3
Labor Hours
210
3
210
30
40
Group of answer choices
$280
$6,980
$250
$6,920
$220

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!