Question: What is the consequence ranking component used to perform a criticality analysis in the calculation of a risk priority number? Group of answer choices Rate
What is the consequence ranking component used to perform a criticality analysis in the calculation of a risk priority number? Group of answer choices Rate of severity of the effect of the failure Rate the likelihood that failure will occur Rate the likelihood that failure will not be detected Rate of severity of the priority of success
Step by Step Solution
There are 3 Steps involved in it