A contract is started on 1 January 2015, with an estimated completion date of 31 December 2016.
Question:
A contract is started on 1 January 2015, with an estimated completion date of 31 December 2016. The final contract price is $1,500,000.
In the first year, to 31 December 2015:
• Costs incurred amounted to $600,000.
• Half the work on the contract was completed.
• Certificates of work completed have been issued, to the value of $750,000. (Note. It is usual, in a construction contract, for a qualified person such as an architect or engineer to inspect the work completed, and if it is satisfactory, to issue certificates. This will then be the notification to the customer that progress payments are now due to the contractor. Progress payments are commonly the amount of valuation on the work certificates issued, minus precautionary retention of 10%).
• It is estimated with reasonable certainty that further costs to completion in 2016 will be $600,000.
What is the contract profit in 2015, and what entries would be made for the contract on 31 December 2015 if:
(a) Profits are deferred until the completion of the contract?
(b) A proportion of the estimated revenue and profit is credited to the profit or loss in 2015?
Fundamentals of Database Systems
ISBN: 978-0136086208
6th edition
Authors: Ramez Elmasri, Shamkant Navathe