Question: What is the correct answer? 1 - A new project to build a four sided fence, each side planned to take 2 days with cost
What is the correct answer?
1 - A new project to build a four sided fence, each side planned to take 2 days with cost of 1000 SR. If you handed with a report on the end of day three showing the following status of the project: Side1 (finished) and cost 950 Side2 (finished) and cost 1100 Side3 (5096 completed) and cost 700 So the project is exactly on planned costo ahead of schedule O Over planned costo under planned cost O