Question: What is the cost estimating technique based on estimating individual work items and summing them to get a project total called? a. Definitive Estimate b.
What is the cost estimating technique based on estimating individual work items and summing them to get a project total called?
a. Definitive Estimate
b. Parametric Estimate
c. Bottom-Up Estimates
d. Analogous Estimates
anesha is managing a project. The original scope baseline of the project was budgeted at $100,000. Since work on the project started there have been seventeen authorized and approved changes to the project. The changes have a value of $17,000 and the cost of investigating them prior to their approval was $2,500. What is the current budget for Tanesha's project?
a.
$100,000
b.
$114,500
c.
$117,000
d.
$119,500
Ashley is the Project Manager for Blue Power Lumber Yard. She is trying to forecast estimates for the last phase of the project that she is currently working on. Based on the performance of the project to date, which formula should she use to estimate the total value of the project when completed assuming similar variances will not occur?
a.
EAC = AC + BAC EV
b.
SV = EV PV
c.
CPI = EV/AC
d.
ETC = (BAC EV)/CPI
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts