Question: What is the cost variance for a project that has a TBC = $50.000, a CEV = $25,000, a CAC = $20,000, and CBC =

What is the cost variance for a project that has
What is the cost variance for a project that has a TBC = $50.000, a CEV = $25,000, a CAC = $20,000, and CBC = $22,000? * O CV = - $2,000 CV = - $5,000 O cv = $5,000 CV = $2,000