Question: what is the cretical path begin{tabular}{|l|l|l|r|} hline & & & hline & & & hline Task ID & Task Description & Task Predecessors
\begin{tabular}{|l|l|l|r|} \hline & & & \\ \hline & & & \\ \hline Task ID & Task Description & Task Predecessors & TaskDuration(hours) \\ \hline A & Project start & & 0 \\ \hline B & Buy materials for A & A & 10 \\ \hline C & Buy materials for B & A & 20 \\ \hline D & Build A & B, C & 30 \\ \hline E & Build B & B, C & 20 \\ \hline F & Polish and finish B & E & 40 \\ \hline G & Join A and B & D, F & 20 \\ \hline H & Project finish & G & 0 \\ \hline \end{tabular}
Step by Step Solution
There are 3 Steps involved in it