Question: What is the critical path? By how many weeks are we 90% sure of completing the project (along the critical path)? Activity Optimistic time Most
What is the critical path? By how many weeks are we 90% sure of completing the project (along the critical path)?

Activity Optimistic time Most likely time Pessimistic time Expected time Variance A 3 6 9 B 3 5 7 4 7 12 D 4 8 10 E 5 10 16 F 3 4 5 G 3 6 8 H 5 6 10 I 5 8 11 J 3 3 3 B(s) D(7.67) FC4) H(6.5) A(6) J(3) I(8) 17.33) E(10.17) G(5.83)