Question: What is the critical path for a project made up of the following activities? Activity Immediate Predecessor Estimated Time A None 6 B None 5

What is the critical path for a project made up of the following activities?
Activity Immediate Predecessor Estimated Time
A None 6
B None 5
C None 8
D A 5
E C 4
F C 10
G B, D, E, F 10