Question: What is the critical path? How long will it take to install the system? The M & M Accounting firm is installing a new computer

What is the critical path?
How long will it take to install the system?
The M & M Accounting firm is installing a new computer system. Several things must be done to make sure that the system works properly before all the accounts are put into the new system. The following table provides information about this project. Activity Immediate Predecessor Time Required (in weeks) 3 --- A B D E F G H A B A CD D, E F. G 4 6 2 5 2 4 5 What is the critical path