Question: What is the critical path in a PERT analysis? Group of answer choices The path with the most number of tasks The sequence of tasks

What is the critical path in a PERT analysis?
Group of answer choices
The path with the most number of tasks
The sequence of tasks with the highest cost
The sequence of tasks that determines the minimum project duration
The path with the least number of tasks

Step by Step Solution

There are 3 Steps involved in it