Question: What is the critical path? What is the project completion time? How long can you delay activity E without endangering the completion time of the
What is the critical path?
What is the project completion time?
How long can you delay activity E without endangering the completion time of the whole project?
This is the information.

Actvity Description Time Immediate Predecessor A Prepare bill of Materials 1 None B Prepare Assembly Charts 3 A C Order and await delivery of materials 4 A D Organize production line 2 B E Specify inspection procedures 1 B LL F Set up inspection stations 2 D,E G Train workers 3 C,D H Assemble products 7 F,G,
Step by Step Solution
3.45 Rating (168 Votes )
There are 3 Steps involved in it
The critical path is the longest sequence of activities in a project plan which m... View full answer