Question: What is the difference between a construction schedule and an estimate schedule? - Construction schedule represents are a series of milestones set in place -
What is the difference between a construction schedule and an estimate schedule?
- Construction schedule represents are a series of milestones set in place
- None of the above
- An estimate schedule are the dates for any estimations and deadlines that are scheduled
- Construction schedule represents anticipated work in place whereas estimate schedule charts the effort necessary to prepare a bid or proposal - pre construction