Question: What is the DL Rate Variance? Please round your answer to the nearest whole dollar and indicate whether the variance is Favorable (F) or Unfavorable



What is the DL Rate Variance? Please round your answer to the nearest whole dollar and indicate whether the variance is Favorable (F) or Unfavorable (U). For Chapter 8 Standard Costing Variances Questions: Unit Standards: DM 20.0 ft @ $ 320.00 DL 18.0 hours @ 324.00 $ 16.00 foot $ 18.00 hour $ 8.00 hour $ 12.00 hour VOH 18.0 hours @ 144.00 FOH 18.0 hours @ = 216.00 1,004.00 Flexible Budget: 14,000 (70%) 280,000.0 ft DM @ $ 16.00 foot DL 252,000.0 hours @ $ 18.00 hour = 1111111 4,480,000.00 4,536,000.00 2,016,000.00 3,024,000.00 VOH 252,000.0 hours @ $ 8.00 hour FOH 252,000.0 hours @ $ 12.00 hour @ 16,000 (80%) DM 320,000.0 ft @ $ 16.00 foot = DL 288,000.0 hours @ $ 18.00 hour 5,120,000.00 5,184,000.00 2,304,000.00 3,024,000.00 VOH 288,000.0 hours @ $ 8.00 hour = FOH = @ 18,000 DM $ 16.00 foot (90%) 360,000.0 ft 324,000.0 hours 324.000.0 hours 5,760,000.00 5,832,000.00 DL @ $ 18.00 hour VOH @ $ 8.00 hour FOH 2,592,000.00 3,024,000.00 18,000 (90%) DM 360,000.0 ft @ 16.00 foot 5,760,000.00 DL $ 18.00 hour 5,832,000.00 324,000.0 hours 324,000.0 hours = = $ 8.00 hour 2,592,000.00 FOH 11 - 3,024,000.00 Actuals: @ 16,000 DM 336,000.0 ft $ 16.50 foot = - 5,544,000.00 @ @ DL 320,000.0 hours $ 17.50 hour IT 5,600,000.00 VOH Il 2,640,000.00 3,520,000.00 FOH i) Planned operation was at 70% of the productive capacity of 20,000 units. ii) Prepare DM, DL, VOH and FOH variance analyses
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts