Question: What is the earliest finish ( EF ) time for activity E ? table [ [ Activity ID , Predecessor,Duration ( in days )

What is the earliest finish (EF) time for activity E?
\table[[Activity ID,Predecessor,Duration (in days)],[A,None,9],[B,A,2],[C,A,3],[D,B, C,7],[E,D,6],[F,E,6],[G,D,1],[H,G, F,4]]
23
25
18
12
 What is the earliest finish (EF) time for activity E? \table[[Activity