Question: What is the earliest time (in weeks) that Activity D can finish? What is the latest time (in weeks) that Activity C can start? What

- What is the earliest time (in weeks) that Activity D can finish?
- What is the latest time (in weeks) that Activity C can start?
- What is the duration and total cost of the project if it is crashed to the maximum extent possible? Your answer should include which activities are crashed and by how many weeks.
The details of a consulting project are provided below The following cost estimates are associated with speeding up the activities of the con