Question: What is the Earliest Time this project can be completed? Briefly explain 1. (90 pts. Consider the below table for a project. Activity Immediate Predecessors

What is the Earliest Time this project can be

  1. What is the Earliest Time this project can be completed? Briefly explain
1. (90 pts. Consider the below table for a project. Activity Immediate Predecessors B D A E AB F A, B, C G D, E, H H E, F Time (weeks) 3 4 2 4 5 2 1 6