Question: What is the early finish time for Activity C based on the provided data in the following table? Activity - Time - Predecessor A -

What is the early finish time for Activity C based on the provided data in the following table?
Activity - Time - Predecessor
A -6---
B -4- A
C -4- B
D -5- B
options:
11
12
13
14

Step by Step Solution