Question: What is the Earned Value ( EV ) at week 1 0 ? Cu l es el valor ganado ( EV ) en la semana

What is the Earned Value (EV) at week 10?Cul es el valor ganado (EV) en la semana 10?
Progress at week 10:
8 printers have been installed
$98,500 spent to date
Assumptions:
It is expected that the project will continue to spend at the same rate up to now.
It is required that we finish the project within the BAC.
The Budget per printer already include the contingency reserve.
Select the correct response:
150,000
98,500
100,000
80,000