Question: What is the ES, EF, LS, LF, TF & FF for Activity D? Select one: a. 3, 7, 17, 16, 29 & 0 b. 3,

What is the ES, EF, LS, LF, TF & FF for Activity D? Select one: a. 3, 7, 17, 16, 29 & 0 b. 3, 8, 15, 16, 22 & 6 c. 3, 8, 10, 26, 32 & 2 d. 2, 9, 16, 23, 14 & 5
What is the ES, EF, LS, LF, TF & FF for Activity J? Select one: a. 24, 26, 28, 30, 4 & 4 b. 21, 22, 27, 35, 2 & 2 c. 25, 31, 32, 30, 3 & 3 d. 27, 28, 29, 31, 5 & 5
What is the project duration?
Select one: a. 29 b. 32 c. None of the above d. 31 e. 30
S Activity Duration ES LS EF FFTF 25/8 D H 10 A E K PS/ 1 FS/2 FS/2Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
