What is the expected NPV for a project with the following scenarios?

Economic scenario probability of outcome NPV (in millions)
Poor 0.2 $(50)
Average 0.6 19
Excellent 0.2 $ 40

Input your answer rounded to 0 decimal places and do not enter any symbols such as $, comma or %.