What is the expected project duration given the following information on project activities and project network diagram?

Select one:
a.
36 days
b.
37 days
c.
34 days
d.
33 days
e.
35 days
Duration 3 days 9 B Immediate Activity Predecessor(s) A B A C B,D D A E A F DE G CF H G . 9. 8 7 8 9" E 21 6Step by Step Solution