Question: What is the expected project duration given the following information on project activities and project network diagram? Select one: a. 36 days b. 37 days

What is the expected project duration given the following information on project activities and project network diagram?

What is the expected project duration given the

Select one:

a.

36 days

b.

37 days

c.

34 days

d.

33 days

e.

35 days

Duration 3 days 9 B Immediate Activity Predecessor(s) A B A C B,D D A E A F DE G CF H G . 9. 8 7 8 9" E 21 6

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!