Question: What is the expected time to complete a task with optimistic, most likely, and pessimistic times of 3 , 4 , and 7 days respectively?

What is the expected time to complete a task with optimistic, most likely, and pessimistic times of 3,4, and 7 days respectively?
Group of answer choices
4.3
3
4
4.7

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!