Question: What is the expected time to complete activity A? What is the expected time to complete activity B? What is the expected time to complete

What is the expected time to complete activity A?
What is the expected time to complete activity B?
What is the expected time to complete activity D?
What is the variance for activity E?
What is the expected time to complete the project?
What is the variance of the project's total completion time?
What is the probability that the project will be completed in 34 weeks or less?
What is the probability that it will take more than 34 weeks to complete the project?
What are the activities in the critical path?
Activity a b Predecessor m 5 A 3 7 B 4 8 10 | 2 3 5 A D 6 9 12 B, C E E un 5 9 15 D
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts