Question: What is the impact of additional setups and setup time of cutting batch sizes for non - bottleneck parts in half? Question 6 Select one:

What is the impact of additional setups and setup time of cutting batch sizes for non-bottleneck parts in half?
Question 6 Select one:
a.
It causes self-created bottlenecks that Alex is able to eliminate through proper release of material.
b.
All of these are correct.
c.
It doesnt matter since it occurs only with non-bottleneck operations.
d.
It increases the lead time throughout the plant due to additional processing time.