Question: What is the impact of additional setups and setup time of cutting batch sizes for non - bottleneck parts in half? Question 6 Select one:
What is the impact of additional setups and setup time of cutting batch sizes for nonbottleneck parts in half?
Question Select one:
a
It causes selfcreated bottlenecks that Alex is able to eliminate through proper release of material.
b
All of these are correct.
c
It doesnt matter since it occurs only with nonbottleneck operations.
d
It increases the lead time throughout the plant due to additional processing time.