Question: What is the latest finish for activity E ? Enter the numerical value for the number of weeks. table [ [ Project activity precedence

What is the latest finish for activity E? Enter the numerical value for the number of weeks.
\table[[Project activity precedence diagram and activity times:,,,,,,],[Activity,Duration (wk),Activity,Duration (wk),Plan,Deslen,Bulld,Test,Produce,i]],[A,2,T,2,,,,,,],[B,3,u,2,,D,B,,,],[c,5,v,8,,,,,,],[D,6,w,9,,C,G,H,,],[E,2,x,5,,,,,,],[F,10,Y,11,A,E,U,T,Z,End],[\table[[G],[H
 What is the latest finish for activity E? Enter the numerical