Question: What is the LS, LF and slack for each task and explain why CRITICAL PATH TASK ES EF LS LF SLACK 01- Develop Plan 2

What is the LS, LF and slack for each task and explain why

What is the LS, LF and slack for each task and explain

CRITICAL PATH TASK ES EF LS LF SLACK 01- Develop Plan 2 02- Assign Tasks 2 5 03- Obtain Hardware 2 18 04- Programming 6 75 05- Install Hardware 19 28 06- Program Test 76 105 07- Write User Manual 29 53 08- Convert Files 29 48 09- System Test 54 106 73 130 106 130 10- User Training 106 130 106 130 OO 11- User Test 131 155 131 155 PATHS Path A: 1-2-4-6-9-11 - 155 CRITICAL Path B: 1-3-5-7-10-11 - 98 Path C: 1-3-5-8-10-11 - 93