Question: What is the max cycle time for the following process? (Keep one decimal place) Task Immediate Predecessor Task Time (in minutes) A - 0.3 B

What is the max cycle time for the following process? (Keep one decimal place)

Task

Immediate Predecessor

Task Time (in minutes)

A

-

0.3

B

A

0.8

C

-

0.7

D

C

0.3

E

B

0.3

F

D, E

1.0

G

F

0.4

H

G

0.3