What is the max cycle time for the following process? (Keep one decimal place)
| Task | Immediate Predecessor | Task Time (in minutes) |
| A | - | 0.3 |
| B | A | 0.8 |
| C | - | 0.7 |
| D | C | 0.3 |
| E | B | 0.3 |
| F | D, E | 1.0 |
| G | F | 0.4 |
| H | G | 0.3 |