What is the net present value of a project with the following end-of-year cash flows if the
Fantastic news! We've Found the answer you've been seeking!
Question:
What is the net present value of a project with the following end-of-year cash flows if the discount rate is 12%?
Year Cash Flow
0 $ 27 500
1 14 800
2 19 400
3 5 200