Question: What is the planned order release using an MRP program if the gross requirement is 125 tons of steel, inventory on hand is 43 tons
What is the planned order release using an MRP program if the gross requirement is 125 tons of steel, inventory on hand is 43 tons of steel, and planned receipts are 47 tons of steel?