Question: What is the Planned Value based on the info below? Project duration - 1 2 months Project Cost ( BAC ) - $ 1 0

What is the Planned Value based on the info below?
Project duration -12 months
Project Cost (BAC)-$100,000
Time elapsed -6 months
Percent complete -50%(as per the schedule)
a. $500,000
b. $5,000
c. $50,000
d. $10,000