Question: What is the potential downside to bringing project workers into a project too early?a . People don't like being told what to do , but
What is the potential downside to bringing project workers into a project too early?a People don't like being told what to do but are usually enthusiastic if they can participate in creating the project plan.b When the people who perform the work help to plan it many more details may be considered.c Bringing SMEs on board before they are needed to complete the project could be expensive.d For external projects, it is common to list the specific workers who will be assigned to a project team in the proposal.