Question: What is the probability that the project (stated in the text below) will be completed within 14 days . Provide your answer to the nearest

What is the probability that the project (stated in the text below) will be completed within 14 days . Provide your answer to the nearest hundredth of a percentWhat is the probability that the project (stated in the text below) will be completed within 14 days .

Activity Precedence

Normal

a

Time

m

Weeks

b

A -- 1 3 5
B A 2 4 8
C A 1 4 12
D A 2 4 5
E C,D 1 2 2
F B,E 1 2 6