Question: What is the probability that the project will be completed on or before a 72-week deadline? Refer to the given z-table. Z-score: Table entry.
What is the probability that the project will be completed on or before a 72-week deadline? Refer to the given z-table. Z-score: Table entry. Standard Normal Probabilities 684994 Table entry for z is the area under the standard normal curve to the left of 2. .00 .02 .03 04 05 06 08 5239 5319 5714 6103 .6406 .6443 6480 6772 .6808 .6844 6985 7019 7054 7088 7123 7157 7190 01 0.0 5000 5040 5080 5120 5160 5199 0.1 5398 .5438 5478 .5517 5557 5596 5636 0.2 .5793 5832 5871 5910 5948 5987 .6026 0.3 6179 6217 6255 .6293 .6331 .6368 0.4 .6554 .6591 .6628 .6664 .6700 .6736 0.5 6915 .6950 0.6 7257 7291 0.7 0.8 7881 0.9 .8159 .8413 .8643 1.2 8849 1.3 .9032 7486 7517 7580 7611 7764 .7794 7823 7910 7939 .7967 .7995 8051 8078 8106 7324 7357 7389 7422 7454 7642 7673 7704 7734 8023 8289 8531 8554 .8577 8599 8729 8749 .8770 8790 8810 .8962 8980 .8315 8340 .8365 8186 .8212 .8438 .8461 .8665 .8686 .8708 8869 .8888 .8907 .8925 9049 9066 9082 9099 9115 .8238 8264 8485 8508 8944 .8997 9131 9147 .9162 (Show your computation below.) 07 5279 5675 6064 .09 5359 .5753 .6141 6517 6879 .7224 .7549 .7852 8133 8389 8621 8830 .9015 9177
Step by Step Solution
There are 3 Steps involved in it
SOLUTION IN DETAILS To find the probability that the ... View full answer
Get step-by-step solutions from verified subject matter experts