Question: What is the probability that this project will be completed less than 21 days and 12 hours? a. 0.0292 b. 0.1280 c. 0.0934 d. 0.5000

What is the probability that this project will be completed less than 21 days and 12 hours?
a. 0.0292
b. 0.1280
c. 0.0934
d. 0.5000
What is the probability that this project will be
1. Consider the following project network. The activity durations (in days) are shown in the nodes, the variance of all activities is 1 day except for activities D, F, and G; their variance is 2 days