Question: What is the project cash flow in year 4 for this project? A project requires buying some fixed assets that cost $40,000 immediately. These fixed

What is the project cash flow in year 4 for this project?

A project requires buying some fixed assets that cost $40,000 immediately. These fixed assets will be depreciated straight-line to zero over its 4-year life. The project also requires a net working capital investment of $5,000 up front. The investment in NWC will recovered fully at the end of the life of the project. The project generates OCF of $17,000 each of the next three years, and the fixed assets will be sold for $7,000 after the four years. Assume that the tax rate for the firm is 34%.

$26,620

$19,620

$21,620

$29,000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!