Question: What is the project duration in days? Question 41 options: 40 or less 42 44 46 48 or more What is the critical path? Question

What is the project duration in days? Question 41

What is the project duration in days?

Question 41 options:

40 or less

42

44

46

48 or more

What is the critical path?

Question 42 options:

Path containing A and B

Path containing B and F

Path containing C and G

Path containing D and H

Path containing E and I

What activity has the greatest float or slack?

Question 43 options:

B

C

D

E

F

What path is near critical?

Question 44 options:

Path containing A and G

Path containing B and F

Path containing C and G

Path containing D and H

Path containing E and I

If a contingency buffer could be added, where would you place it?

Question 45 options:

Between activities A and D

Between activities D and H

Between activities F and I

Between activities H and I

Between activities I and J

Critical Path Method Problem A short project has the activities and dependencies shown on this table. Use this information to draw a network diagram, perform any needed analysis, and answer the following five questions. Activity Predecessor Duration (days) 2 A B 10 A 9 A A D 15 E 20 A F 14 B, C G 12 H 15 D E, F, G, H | 8 J 6 |

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!