Question: What is the project duration in days? Question 41 options: 40 or less 42 44 46 48 or more What is the critical path? Question

What is the project duration in days?
Question 41 options:
|
| 40 or less |
|
| 42 |
|
| 44 |
|
| 46 |
|
| 48 or more
|
What is the critical path?
Question 42 options:
|
| Path containing A and B |
|
| Path containing B and F |
|
| Path containing C and G |
|
| Path containing D and H |
|
| Path containing E and I |
What activity has the greatest float or slack?
Question 43 options:
|
| B |
|
| C |
|
| D |
|
| E |
|
| F |
What path is near critical?
Question 44 options:
|
| Path containing A and G |
|
| Path containing B and F |
|
| Path containing C and G |
|
| Path containing D and H |
|
| Path containing E and I |
If a contingency buffer could be added, where would you place it?
Question 45 options:
|
| Between activities A and D |
|
| Between activities D and H |
|
| Between activities F and I |
|
| Between activities H and I |
|
| Between activities I and J |