Question: . What is the project scope? A . It is the design of experiments used to complete the project work. B . It is the

. What is the project scope?
A. It is the design of experiments used to complete the project work.
B. It is the combination of the cost and the schedule required to complete the
project work.
C. It is the description of the required work, and only the required work, that is
necessary to complete the project.
D. It is the description of the required work and resources needed to complete
the project.