Question: What is the project total cost (direct + indirect) when she has reduced the project duration from 20 to 19 weeks? Question 7 options: 8,950

What is the project total cost (direct + indirect) when she has reduced the project duration from 20 to 19 weeks?

Question 7 options:

8,950

$8,340

$8,400

$9,140

$8,750