Question: What is the pumping rate ( in m 3 d ) required to create a drawdown of 2 7 9 m m at 3 4

What is the pumping rate (in m3d) required to create a drawdown of 279mm at 34.9m from the well after 2.3 days of pumping. The aquifer is confined, and is 21.9m thick and has a K of 5.8md. Take the specific storage as 1.910-51m.
To solve this problem, please use the reduced form of the well equation solution as given here (see the Week 8 lecture on pumping tests for a complete explanation):
-0.5772-ln(u)+u-u22.2!+u33.3!
What is the pumping rate ( in m 3 d ) required to