Question: What is the relationship between IRR and WACC when a project's NPV < 0? Group of answer choices ( ) IRR = WACC ( )
What is the relationship between IRR and WACC when a project's NPV < 0?
Group of answer choices
( ) IRR = WACC
( ) IRR > WACC
( ) IRR < WACC