Question: What is the relationship between strategy and implementation planning in projects? 1 point A . Strategy focuses on long - term objectives, while implementation planning
What is the relationship between strategy and implementation planning in projects?
point
A Strategy focuses on longterm objectives, while implementation planning addresses logistics
B Strategy handles technical details, while implementation deals with customer relations
C Strategy is about resource allocation, while implementation defines success metrics
D Strategy replaces the need for detailed planning
What is a common pitfall of the project definition stage?
point
A Overinvolvement of stakeholders
B Vague initial definitions
C Lack of technical expertise
D Overemphasis on documentation
What is the primary benefit of a "pain curve" in project planning?
point
A It visualizes project budgets over time
B It highlights the impact of early planning on reducing future stress
C It measures employee satisfaction during projects
D It predicts failure points in execution
What is a critical element of proactive project planning?
point
A Avoiding risk documentation
B Using informal problem statements
C Defining mission statements and objectives clearly
D Relying solely on past project data
What principle should guide handling project changes?
point
A Avoid documenting the causes of changes
B Allow changes for minor deviations from targets
C Implement changes following a standard procedure
D Overdetail plans to prevent changes
Which phase involves task monitoring and corrective actions?
point
A Concept Phase
B Execution Phase
C Definition Phase
D Closeout Phase
How should risks be managed during the planning process?
point
A Use only reactive strategies for risk response
B Develop contingency plans for likely scenarios
C Ignore lowprobability risks
D Focus on shortterm risk avoidance
What is a key challenge with dualrole project managers?
point
A They focus too much on team collaboration
B They prioritize team needs over project goals
C They experience conflicts between managing and executing
D They overestimate resource availability
What is a primary function of the project closeout phase?
point
A Define new project objectives
B Reflect on project success and areas for improvement
C Monitor ongoing tasks
D Assign blame for project failures
Which strategy improves project definition success?
point
A Relying solely on leadership decisions
B Ensuring early clarity of the problem and goals
C Avoiding team input in the early stages
D Using generalized problem statements
Why is it critical to align project goals with an organization's mission?
point
A To meet individual stakeholder expectations
B To secure additional funding
C To ensure project outcomes contribute to organizational objectives
D To reduce the need for project documentation
What should a project manager avoid during execution?
point
A Monitoring progress regularly
B Making unstructured adjustments to the plan
C Applying corrective actions when needed
D Communicating with stakeholders frequently
Which practice is essential for effective planning sessions?
point
A Avoid involving those who implement the plan
B Schedule unstructured meetings for flexibility
C Use agendas and facilitators to maintain focus
D Delegate planning to upper management only
What is the primary reason "accidental project managers" often struggle in their role?
point
A They lack access to project management tools
B They fail to align projects with organizational goals
C They perform dual roles, leading to role conflicts
D They rely heavily on standardized procedures
What is a key insight from the project management "pain curve"?
point
A Projects without early planning require more resources later
B Proactive planning increases longterm project costs
C Reactive adjustments during execution improve outcomes
D Minimal effort in planning reduces complexity overall
Which of the following is a critical component of effective risk management in project planning?
point
A Ignoring lowimpact risks
B Prioritizing risks solely by financial implications
C Developing contingencies for highprobability risks
D Allocating resources evenly across all risks
What common misconception about project managers leads to inefficiencies?
point
A They are solely responsible for project execution
B They can lead without formal authority
C They can manage projects effectively without planning
D They should actively participate in executing tasks
What distinguishes a welldefined mission statement in project planning?
point
A It focuses on individual goals over team objectives
B It aligns with the problem statement and user needs
C It emphasizes shortterm results over longterm outcomes
D It excludes logistics and tactics for implementation
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer