Question: What is the Schedule Performance Index ( SPI ) ? Figure 1 : You have a project to build a new fence. The fence is
What is the Schedule Performance Index SPI
Figure : You have a project to build a new fence. The fence is foursided as shown. Each side si to take one day to build and is budgeted for $ per side. The sides are planned to be completed one after the other. Today is the end of day three.
Key: S Actual Start, F Actual Finish, PSPlanned Start, PFPlanned Finish
Activity Day Day Day Day Status End of Day
Side S F Complete, $
Side S PF F Complete, $
Side PS S PF half complete, $
Side PS PF not yet started
Group of answer choices
which is behind schedule
which is behind schedule
which is ahead of schedule
None of the above
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
