Question: What is the Schedule Performance Index ( SPI ) ? Figure 1 : You have a project to build a new fence. The fence is

What is the Schedule Performance Index (SPI)?
Figure 1: You have a project to build a new fence. The fence is four-sided as shown. Each side si to take one day to build and is budgeted for $1,000 per side. The sides are planned to be completed one after the other. Today is the end of day three.
Key: S= Actual Start, F= Actual Finish, PS=Planned Start, PF=Planned Finish
Activity Day 1 Day 2 Day 3 Day 4 Status End of Day 3
Side 1 S --------------- F Complete, $1,000
Side 2 S ------------- PF ----F Complete, $1,000
Side 3 PS ------ S ------- PF half complete, $600
Side 4 PS --------------- PF not yet started
Group of answer choices
.83, which is behind schedule
1.2, which is behind schedule
.83, which is ahead of schedule
None of the above

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!